Measure the scope
Start with dimensions, quantities and a clear description of the work.
A total invites questions. A clear scope, quantity, rate and set of assumptions give you the basis to answer them.
For a house, fit-out or civil works package, define what the estimate includes. Separate concrete, masonry, finishes and other work packages so omissions and double counting are easier to spot.
Use the current drawing revision. Record units and measurement basis before applying prices. A net area is not automatically a purchase quantity; allowances and commercial package rounding may still be required.
Try the calculatorsStart with dimensions, quantities and a clear description of the work.
Apply your supplier quotations, labor rates and explicit allowances.
Review purchasing quantities, crews, equipment and working days.
Keep assumptions visible and take a clear report into the discussion.
Measure each item in its stated unit. Slab area in m² is different from concrete volume in m³; make thickness explicit before converting.
Record quoted rate, specification, source, date, and whether delivery or tax is included. Compare quotations on the same basis.
Identify included work, exclusions and items awaiting confirmation. Bring those assumptions into the report so the next review has context.
A 10 m × 8 m × 0.15 m slab measures 12 m³. A 5% planning allowance gives 12.60 m³. At an illustrative ₱5,000/m³, the concrete material subtotal is ₱63,000. Reinforcement, formwork, labor, equipment and other scope remain separate.
TB is a planning tool. Review project scope, supplied inputs, engineering design and applicable local requirements.